Project Role & Details
Client: Wisconsin Central Railroad
Location: Chippewa Falls, WI
Contractor Project Manager. The scope of services included the removal and replacement of 11, 105-foot spans of a railroad bridge over the Chippewa River near Chippewa Falls, WI . Span removal and replacement was performed within restrictive rail down-time windows. This project also included the construction of a temporary bridge and causeway in the Chippewa River equipment/crane access and other construction staging activities. Coordinated WDNR permitting to allow construction while minimizing negative impacts to the river.